P6 Activity Duration Calculator
What is a P6 Activity Duration Calculator?
In Primavera P6, each activity needs an original duration. Guessing durations leads to unrealistic schedules; deriving them from quantities and production rates makes the schedule defensible and easy to update. This calculator converts a quantity of work, a crew's daily output and the number of crews into an activity duration in working days.
How to use it
- Enter the work quantity from the BOQ or take-off, such as 450 m² of formwork.
- Enter the production rate of one crew per day, such as 30 m² per crew-day.
- Enter the number of crews and, optionally, working hours per day.
- Read the duration and round it to whole days for P6.
The formula
Duration (days) = Quantity / (Output per crew per day × Number of crews)
Worked example
Blockwork of 1,200 m², one crew of 2 masons and 2 helpers produces 20 m² per day. With 3 crews: 1,200 / (20 × 3) = 20 working days. With 2 crews it becomes 30 days, which shows the trade-off between resources and time.
Making durations realistic
- Use proven production rates from your company's historical data or recognised norms, adjusted for site conditions.
- Apply efficiency factors for weather, height, congestion and learning curve, often 0.7 to 0.9.
- Respect crew limits: adding crews only helps if there is enough workspace; doubling crews rarely halves the duration on a congested floor.
- Match the calendar: P6 durations are in working days of the activity's calendar, so a 6-day week calendar finishes sooner in calendar time than a 5-day one.
- Record the quantity and rate in activity notes or user-defined fields so the logic can be audited.
Frequently Asked Questions
How do I calculate an activity duration?
Divide the quantity of work by the daily output of one crew multiplied by the number of crews.
Should I round the duration?
Yes. P6 usually works in whole days or hours, so round up to avoid underestimating.
Does adding more crews always shorten the activity?
Only if there is enough workspace and material supply. Congestion often reduces the benefit of extra crews.
Where do production rates come from?
From historical project data, estimating handbooks and contractor experience, adjusted for the specific site conditions.