Planned Value Calculator
What is a Planned Value Calculator?
Planned Value (PV), also called Budgeted Cost of Work Scheduled (BCWS), is the budgeted value of the work that should have been completed by a given date according to the baseline schedule. It is the yardstick for schedule performance in earned value management: comparing PV with Earned Value shows whether the project is ahead or behind.
How to use the calculator
- Enter the Budget at Completion (BAC) of the activity or project.
- Enter the planned percent complete at the status date from the baseline schedule, or the planned start, finish and status dates for a linear spread.
- Read the Planned Value, and optionally compare it with EV.
Formulas
PV = BAC × planned % complete at status date- For a linear plan:
planned % = elapsed planned duration / total planned duration SV = EV - PVandSPI = EV / PV
Worked example
A road subbase package has a BAC of 1,200,000, planned to run evenly over 12 weeks. At the end of week 5, planned progress is 5 / 12 = 41.7%, so PV = 500,000. If the measured EV is 420,000, SV = -80,000 and SPI = 0.84: the work is about 16% behind schedule.
Building PV properly
- PV comes from the baseline, not the current schedule. Re-baselining changes PV and must be controlled.
- Cost-loaded schedules in P6 produce a PV curve automatically from resource assignments.
- Many activities are not linear: earthworks and finishes often follow an S-curve, slow at the start and end.
- The cumulative PV over time forms the familiar S-curve used in progress reports.
Frequently Asked Questions
What is Planned Value?
The budgeted value of the work scheduled to be completed by a given date, according to the baseline plan.
What is the difference between Planned Value and Earned Value?
Planned Value is the work that should be done by now. Earned Value is the work actually done, both measured in budget terms.
Is Planned Value the same as BCWS?
Yes. BCWS, Budgeted Cost of Work Scheduled, is the older name for Planned Value.
What is a PV S-curve?
A chart of cumulative Planned Value over time, typically S-shaped because progress is slow at the start and end of a project.